Skip to content

80/90 Distribution Center

Location: 24605 Cleveland Rd. | South Bend, IN
Project Type: New construction of a flex-industrial facility
Project Cost: $10.1 million
Size: 225,000 Square Feet
Owner: 31 Nimtz Land, LLC
Architect: Curran Architecture, Abonmarche Civil engineering
Project Manager: Scott DeMartinis
Start Date: October 2019
Completed: September 2020

Scope:
The South Bend office has completed construction of a 225,000 square foot Pre-Engineered Metal Building consisting of an 8′ high split face masonry façade and insulated metal panels above. The building features interior elevations of 36′ and column spacing at 50′ x 50′ and was designed to accommodate 1-4 future tenants. The facility has 20 dock doors, with the ability to add 20 additional dock doors in the future. The sitework included a large asphalt parking lot with concrete curbs, new landscaping and two entrances off of Cleveland Road. The project broke ground in October 2019 and was completed in September 2020.